Kitchen Progress 02/2026
- Feb 26
- 1 min read
Spring is just around the corner, and it couldn't come soon enough. Progress on the kitchen has been moving right along and is going well despite quite a few winter storms Mother Nature decided to throw our way. So far this month, the soffit/facia, and exterior doors/frames have been fully installed. The siding has been delivered with installation being completed the week of 2/23. The roofing has also been delivered onsite, but awaits a break in the weather to be installed. As for inside the building, the under slab plumbing work has begun, and the electrical work is currently being planned.