Kitchen Progress 03-05/2026

  • 1 day ago
  • 1 min read

The Empire crew is maintaining momentum on the RMSC kitchen project, despite the recent heatwave.

Here is what has been completed in these last few busy months:

  • Interior concrete slab poured

  • Electrical pole installed and wired into the building

  • Plumbing, HVAC, and Electrical rough-in completed

  • Gutters and downspouts

  • Generator installed

  • Concrete for new sidewalk slabs and delivery driveway poured

  • Exterior doors installed

  • Insulation installed

  • Drywall installation started week of 5/18

There is a lot left to be finished but the list shrinks day by day. Included on the upcoming schedule are projects such as: flooring, paint/primer, and FRP installation in kitchen area; Additional project dates are TBD in the upcoming weeks. The kitchen is expected to be completed beginning/mid July.


 
 
 