Kitchen Progress 03-05/2026
- 1 day ago
- 1 min read
The Empire crew is maintaining momentum on the RMSC kitchen project, despite the recent heatwave.
Here is what has been completed in these last few busy months:
Interior concrete slab poured
Electrical pole installed and wired into the building
Plumbing, HVAC, and Electrical rough-in completed
Gutters and downspouts
Generator installed
Concrete for new sidewalk slabs and delivery driveway poured
Exterior doors installed
Insulation installed
Drywall installation started week of 5/18
There is a lot left to be finished but the list shrinks day by day. Included on the upcoming schedule are projects such as: flooring, paint/primer, and FRP installation in kitchen area; Additional project dates are TBD in the upcoming weeks. The kitchen is expected to be completed beginning/mid July.































Comments